The Principal recently passed on a Report On Recent
Developmental Projects and some good news as follows:
Dear Co Alumnus,
BREAKING NEWS .. 'Ekiti State govt has decided to hand schools taken over in
the 1970s back to the original owners and Alumni Associations"! Dear
compatriot, remain steadfast in the struggle for the sake of Christ whose name
we bear. Victory is in sight. Christ in deed is our Cornerstone.
I'll keep you posted on further developments.
UP SCHOOL !!!
Sincere compliments
M.A. Fasanmade (principal)
June 2007
-------------------------------------------------------------------------------------------------------------------
Report of the Committee on Project Christ's School Renewal.
Volume 1 - Main Report. December 2003
Report of the Committee on Project Christ's School Renewal.
Volume 2 - Annexes to the Main Report. December 2003
-------------------------------------------------------------------------------------------------------------------
PROPOSALS FOR THE PHASED RENEWAL OF CHRIST'S SCHOOL, ADO - EKITI
The Local Organising Committee (LOC) of Christ's School, Ado -Ekiti December
2006(Reunion 2006) meeting in Lagos on Sunday, 9th July, 2006, in the residence
of Erastus Akingbola, among other decisions mandated the members of the Abuja
Chapter of the Alumni Association present to present a draft Proposal for the
Phased Renewal of the School against the background that all the funds needed
for the renewal might not be available at a go and even if it were available,
it was not advisable in view of the current Government Policy and the
organizational and executive capacity available to the Old Students to
executive the Renewal in a single swoop. The Abuja group held two meetings and
the result of the deliberations, which is the Draft Proposal for the Phased
Renewal is commended to the LOC as follows:-
GENERAL ENVIRONMENT OF THE RENEWAL
It was our view that the plan and strategy for the renewal must take into
consideration the current Ekiti State Government Policy Guidelines on Secondary
Schools. The relevant issues are:- . A public secondary schools should not
operate boarding facilities for students; . A public secondary school should
draw her students from its catchment area so that the students should come from
three(3) kilometers of the location of the school; . The Free Education
Programme in public secondary schools which therefore means that free tuition
The Policy environment became important for our assignment because it
established two clear options:
Option 1:
If the Ekiti State Government continue to own the School, the intervention of
the old students must be focused on the improvement of instructional
facilities, curriculum development, staff improvement, partnership with the
Government to ensure the long tenure and stability for the Principal and the
staff and the crucial issue of ensuring that the Ekiti State Government
continued to sustain the renewed facilities through regular maintenance and
additional development, student and staff improvement through adequate funding,
progressive Government Policy and enlightened and committed management of the
School by the Principal and the Staff. The logic that informed this option is
that there is no sense in substantial renewal of the facilities of the
dormitory areas, if Government Policy discourages the boarding system. Since
the facilities will be fallow, alternative uses, in the longer run,
might be to convert them to additional classrooms and instructional facilities
or the nucleus of the provision of the vertical range of education envisioned
in Paragraph 2.15 of the Project Christ's School Renewal 2003. Even the
alternative-uses-option depends on approval of the Ekiti State Government and
Government Policy Guidelines.
Option 2:
If the School reverts back to private ownership for instance the Old
Students, Anglican Communion and if necessary any other stakeholder. The
intervention must be total focused on the renewal of both boarding and
instructional facilities, curriculum and student renewal, staff and staff
facility renewal and the overhaul of the Administration of the School. The
governance of the School will be in the hands of the private proprietor who can
address development issues on a longer term basis. Though the achievement of
this option is more difficult because of the need to secure the release of the
School form the Ekiti State Government, it seems to offer more sustainable
renewal and future growth especially when the quality of infrastructure and
instructions in many profitably private secondary school, even in Ekiti State,
is considered.
FINANCIAL IMPLICATION OF OPTION 1 (EKITI STATE AS THE PROPRIETOR OF THE
SCHOOL).
Duration - 6-Year Plan of 3 Biannual Plans.
1st Bi-annual Plan Academic Facilities
| Girl's Section |
| 1st Bi-annual Plan Academic Facilities
|
|
|
Naira
|
| 1 |
Renovation JSS 1 Block |
2,000,000.00 |
| 2 |
Fine Art Room |
250,000.00 |
| 3 |
Renovation of JSS 2 Block |
1,000,000.00 |
| 4 |
Computer Laboratory |
7,000,000.00 |
| 5 |
Furniture for JSS 1 & 2 |
4,000,000.00 |
| 6 |
Library |
7,500,000.00 |
| 7 |
Technical Workshop |
1,500,000.00 |
| 8 |
Home Economics Room |
2,500,000.00 |
| 9 |
Toilets (Academic and Dormitory Areas) |
3,600,000.00 |
| 10 |
30 KVA Solar Power System |
4,997,000.00 |
| 11 |
1 borehole with overhead tank |
3,500,000.00 |
| 12 |
School Bus |
5,000,000.00 |
| 13 |
School Chapel |
1,000,000.00 |
| 14 |
Rehabilitation of Fence |
2,000,000.00 |
|
|
45,847,000.00 |
| 2nd Bi-annual Plan |
| 1 |
Renovation JSS 3 Block |
400,000.00 |
| 2 |
Renovation SSS 1 Block |
1,500,000.00 |
| 3 |
Furniture for JSS3 & SSS1 |
4,000,000.00 |
| 4 |
Language Laboratory |
3,000,000.00 |
| 5 |
Break room for students |
1,000,000.00 |
| 6 |
Staff Rooms/Offices |
1,800,000.00 |
| 7 |
Break rooms for Teachers |
1,000,000.00 |
| 8 |
Administrative Block |
1,000,000.00 |
| 9 |
Principal's office |
500,000.00 |
| 10 |
Gate House |
1,500,000.00 |
| 11 |
Dinning Room
|
5,000,000.00 |
| 12 |
Buttery |
500,000.00 |
|
|
21,200,000.00 |
| 3rd Bi-annual Plan |
| 1 |
Renovation of SSS 2 Block |
1,500,000.00 |
| 2 |
Renovation of SSS3 Block
|
1,500,000.00 |
| 3 |
Furniture for SSS 2 & 3 |
4,000,000.00 |
| 4 |
Sports Field Upgrade |
800,000.00 |
| 5 |
Sports Equipment & Facilities |
1,000,000.00 |
|
|
8,800,000.00 |
| Boy's Section |
| 1st Bi-annual Plan Academic Facilities
|
| 1 |
Renovation JSS 1 Block |
825,000.00 |
| 2 |
Renovation JSS 2 Block |
1,855,400.00 |
| 3 |
Furniture for JSS 1 & 2
|
4,000,000.00
|
| 4 |
Technical Workshop |
1,661,280.00 |
| 5 |
Computer Laboratory |
1,000,000.00 |
| 6 |
Renovation Fine Art Building |
654,850.00 |
| 7 |
Quadrangle |
3,551,680.00 |
| 8 |
Library |
5,000,000.00 |
| 9 |
School Chapel |
5,000,000.00 |
| 10 |
School Bus |
5,000,000.00 |
| 11 |
2 Boreholes with overhead tanks |
7,000,000.00 |
| 12 |
10 Toilets (School/Dormitory areas) |
4,500,000.00 |
| 13 |
30 KVA Solar Power System |
4,997,000.00 |
|
|
45,044,360.00 |
| 2nd Bi-annual Plan |
| 1 |
Renovation of JSS 3 Block |
2,147,600.00 |
| 2 |
Renovation of SSS1 |
3,530,180.00 |
| 3 |
Furniture for JSS 3 & SSS 1 |
4,000,000.00 |
| 4 |
Renovation Principal's Office |
823,900.00 |
| 5 |
Alumni Centre |
1.200,000.00 |
| 6 |
School Fence Repair |
2,000,000.00 |
| 7 |
Agric/Integrated Science Laboratory |
5,700,000.00 |
| 8 |
Language Laboratory |
1,850,000.00 |
| 9 |
Sports House & Equipment |
1,500,000.00 |
| 10 |
Documentation Centre |
642,405.00 |
| 11 |
Staff and Break Room |
1,800,000.00 |
|
|
23,694,085.00 |
| 3rd Bi-annual Plan |
| 1 |
Renovation SSS 2 Block |
3,615,680.00 |
| 2 |
Renovation SSS 3 Block |
2,057,430.00 |
| 3 |
Furniture SSS 2 & 3 |
4,000,000.00 |
| 4 |
Biology Laboratory |
2,183,580.00 |
| 5 |
Physics Laboratory |
1,712,230.00 |
| 6 |
Chemistry Laboratory |
2,516,495.00 |
| 7 |
Hall of Fame |
600,000.00 |
| 8 |
School Field & Pavillon |
2,900,000.00 |
| 0 |
Sports House & Equipment |
1,500,000.00 |
|
|
21,085,415.00 |
Option 2
In addition to the expenditure in each of the three Bi-annual Plans in Option 1,
the following additional funding will be required.
| Girl's Section |
| 1st Bi-annual Plan |
| 1 |
Partial renovation of Harding House |
750,000.00 |
| 2 |
Furniture |
1,600,000.00 |
| 3 |
Partial renovation of Green House |
450,000.00 |
| 4 |
Furniture |
1,600,000.00 |
| 5 |
Partial Renovation of White House |
330,000.00 |
| 6 |
Furniture |
1,600,000.00 |
| 7 |
Partial renovation of Blue House |
330,000.00 |
| 8 |
Furniture |
1,600,000.00 |
| 9 |
Partial Renovation of Red House |
330,000.00 |
| 10 |
Furniture |
1,600,000.00 |
| 11 |
Sick Bay |
450,000.00 |
| 12 |
Renovation of Principal's House |
1,300,000.00 |
|
|
11,940,000.00 |
| 2nd Bi-annual Plan |
| 1 |
Partial Renovation of Dorm |
2,640,000.00 |
| 2 |
Furniture |
8,000,000.00 |
| 3 |
Renovation of Roads |
10,000,000.00 |
| 4 |
Drainage 1st Phase |
5,000,000.00 |
| 5 |
Street Lighting |
2,800,000.00 |
|
|
28,400,000.00 |
| 3rd Bi-annual Plan |
| 1 |
Final Renovation of Dorm |
2,640,000.00 |
| 2 |
Furniture |
8,000,000.00 |
| 3 |
Renovation of Staff Quarters (See Details on Annex II, page 2, Sec
23 of Report) |
6,824,100.00 |
| 4 |
Geographical Garden |
500,00.00 |
| 5 |
Agric Projects |
1,875,000.00 |
|
|
19,839,000.00 |
| Boy's Section |
| 1st Bi-annual Plan |
| 1 |
Partial Renovation of Dallimore Blks 1 & 2 |
900,000.00 |
| 2 |
Dallimore 3, Harding 3 & C/Room |
1,500,000.00 |
| 3 |
Harding Blks 1 & 2 |
450,000.00 |
| 4 |
Furniture Dallimore and Harding |
3,200,000.00 |
| 5 |
Mason Blks 2 & 3 |
450,000.00 |
| 6 |
Mason1, Bab 1 & C/Room |
1,500,000.00 |
| 7 |
Babamboni 2 & 3 |
400,000.00 |
| 8 |
Furniture Mason and Babamboni |
3,200,000.00 |
| 9 |
Ogunlade Blks1, 2 & 3 |
675,000.00 |
| 10 |
Furniture Ogunlade |
1,600,000.00 |
| 11 |
School Gate |
1,000,000.00 |
|
|
14,875,000.00 |
| 2nd Bi-annual Plan |
| 1 |
Renovation of Dormitories |
5,875,000.00 |
| 2 |
Furniture for Dormitories |
8,000,000.00 |
| 3 |
Renovation of Staff Quarters (See Annex II, page 5 & 6 for
details) |
6,000,000.00 |
| 4 |
Drainage |
10,000,000.00 |
| 5 |
Roads |
7,500,000.00 |
| 6 |
Street Lighting |
2,800,000.00 |
|
|
40,175,000.00 |
| 3rd Bi-annual Plan |
| 1 |
Renovation of Dormitories |
5,875,000.00 |
| 2 |
Furniture for Dormitories |
8,000,000.00 |
| 3 |
Renovation of Staff Quarters (See Annex II, page 5 & 6 for
details) |
5,856,000.00 |
| 4 |
Drainage |
5,000,000.00 |
| 5 |
Roads |
2,500,000.00 |
| 6 |
Geographical Garden |
150,000.00 |
| 7 |
Botanical Garden |
100,000.00 |
| 8 |
Zoological Garden |
800,000.00 |
| 9 |
Commercial Projects |
3,275,000.00 |
|
|
31,556,000.00 |
|